Description of scheduled work:
Phase 1 :
2026
- Underground infrastructure assessment (sanitary, storm sewers and watermain)
- Reconfiguration/Design of lanes for vehicles and pedestrians
2027
- Preparation of plans and tender documents
2028
Construction
Phase 2
2026
- Underground infrastructure assessment (sanitary, storm sewers and watermain)
- Reconfiguration/Design of lanes for vehicles and pedestrians
2027
- Preparation of plans and tender documents
2029 +
- Construction
Road closures
2026-2027
No
2028
To be confirmed
Approved budget 2026
313 000 $
Future budget
TBC