Description of scheduled work:
Phase 3:
2026-2027
- Hydro power line relocation (spring 2026)
- St-Jean Street road reconstruction (start, summer 2026 to summer 2027)
Future Phase(s)
2028 +
Poupart Road reconstruction
Road closures
2026-2027
Poupart Road - Mid October to end of November*
St-Jean Road - Mid November to Spring 2027 *
*Exact dates to be confirmed at a later date
Approved budget
15M
Questions
Image

Dates for work
2026 to 2028+
Road Closures
Yes
Approved Budget
15M