Road Work

Multi-use Trail (Morris Village)

Description - Multi-use trail with stone dust surface

Approximate dates of work - August to September 2021

Approved Budget - $205,000

Contact - Alain Beaulieu abeaulieu@clarence-rockland.com

 
 
**************************************************************

Sidewalk Extension Landry Street

Description : Extension of existing sidewalk, from south extremity to Roxanne Street

Approximate dates of work : August to September 2021

Approved Budget : $200,000

Contact : Charles Bonneau cbonneau@clarence-rockland.com

 

**************************************************************

Street Paving

Description : Pavement of the following streets

  • Laporte Street, from Chamberland to Laurier (Grind and pave)

  • Laurier Street, from Laporte on a distance of 400 m to the west (Pulverize and pave)

Scratch Coat

  • Lemay Circle

  • Liliane Street

  • Côté Street

  • Lise Crescent

  • Dianne Street

  • Lawrence Street

  • Poitras Street

  • Morris Street

  • Des Cèdres Avenue

  • Michel Street

  • Kathy Street

  • Ouellette Street (St-Pascal)

  • Emilia Street (Cheney)

Approximate dates of work : Laporte Street, from Chamberland to Laurier, May 2021 - Other streets : June to October 2021

Approved Budget : $1,400,000

Contact : Alain Beaulieu abeaulieu@clarence-rockland.com

**************************************************************

Double Surface Treatment

Description : Double surface treatment application on the following roads :

  • Indian Creek Road (North)

  • Du Lac Road, from Baseline to the northern limits of the village (St-Pascal)

Approximate dates of work : August to September 2021

Approved Budget : $646,000

Contact: Alain Beaulieu abeaulieu@clarence-rockland.com

 

 
**************************************************************

Edwards Street Reconstruction

Description : Replacement of major underground infrastructure, as well as street repaving between Counties Road 17 and Laurier Street (full width) 

Approximate dates of work : June to November 2021

Approved Budget : $1,680,000 

Contact : Charles Bonneau cbonneau@clarence-rockland.com

 
**************************************************************

McTeer Road Reconstruction

Description : Reconstruction of McTeer Road

Approximate dates of work : June to September 2021

Approved Budget : $250,000

Contact : Alain Beaulieu abeaulieu@clarence-rockland.com

 
**************************************************************

Replacement of a Culvert on Du Lac Road

Description : Replacement of a major culvert, immediately north of Duquette Road

Approximate dates of work : July to August 2021

Approved Budget : $646,000

Contact : Alain Beaulieu abeaulieu@clarence-rockland.com

**************************************************************

Repairs on Three Bridges

Description : Various repairs on the following bridges 

  •       Breabrook Bridge
  •       Larose Bridge
  •       Cobb’s Lake Bridge (on Du Lac Road)

Approximate dates of work : July to October 2021

Approved Budget : $193,000

Contact : Alain Beaulieu abeaulieu@clarence-rockland.com

**************************************************************

Watermain Replacement on Laurier Street

Description: Replacement of the watermain on Laurier Street, between Simoneau and Giroux Streets and repaving the street in its full width. 

Approximate dates : May to November 2022
Approved Budget : 2.14M$
Contact : Charles Bonneau, cbonneau@clarence-rockland.com

 

 

 
 